Ugu update on planned partial emergency plant shutdown

Share the news!!!

Share on facebook
Share on whatsapp
Share on twitter
Share on pinterest
Share on email

STATEMENT BY UGU DISTRICT MUNICIPALITY ON WEDNESDAY MORNING 11/2:

The work on the planned shutdown on Bhobhoyi plant is in progress as from 6am.

Team is busy stripping the two valves to access the gate section.

The plan to continue feeding the southern system has hit a snag due to interlinking valves that were bypassing and water flooding the working site. Both plant reservoir have now been isolated.

Southern system (Seaslopes, Gamalakhe, Uvongo, Shelly beach), Murchison pumps, Marburg/Oslo beach, Northern System all isolated.

With all systems down; alternative filling point in Southbroom is being set up.

Thank you
Ugu District Municipality

 

STATEMENT BY UGU DISTRICT MUNICIPALITY ON TUESDAY 10.2

Ugu would like to remind consumers of the planned partial emergency plant shutdown tomorrow, Wednesday, 11th of March 2020, starting from 6am to 3pm.

We will be stripping and inspecting two supply gate valves on the 450/400 mm mainline to Umzimkhulu command reservoir for Northern system (Albersville, Tweni, Seapark, Sunwich Port, Southport, Melville, Pumula, Woodgrange and Hibberdene including part of KwaMadlala, Louisiana and Fairview).

Marburg, Oslo, Albersville and Margate CBD (2A reservoir), Northern system will be affected as plant reservoir feeding systems (North and 300 south) will be allowed to drain empty before work can commence.

Two southern main (600 mm and 375) will remain live during shutdown work to feed Seaslopes, Gamalakhe and Uvongo.